Garage Improvements
Federal contribution
$2.6M
$2,564,804
Federal share47%
of $5.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 25, 2016
2017201820192020
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Winnipeg
- Construction start
- Apr 9, 2018(actual)
- Construction end
- Feb 28, 2020(actual)