Rural Waterline Expansion

Cartier, Manitoba

completeDrinking WaterCWWF
Federal contribution
$883,151
Federal share29%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 25, 2016
2017
Built
Program
Clean Water and Wastewater Fund
Construction start
Jun 5, 2017(actual)
Construction end
Sep 20, 2017(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2017
  • Construction end13 months earlyforecast Nov 1, 2018

Also in Cartier

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47123 in the federal list. How to read these figures.