Elie Lagoon RipRap Upgrade

Cartier, Manitoba

completeWastewaterCWWF
Federal contribution
$315,665
Federal share21%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 18, 2017
2018
Built

Approved 8 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Sep 18, 2017(actual)
Construction end
May 28, 2018(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2017
  • Construction end8 weeks lateforecast Mar 31, 2018