Miltonvale Wellfield Mechanical/Electrical
Charlottetown, Prince Edward Island
Federal contribution
$1.4M
$1,400,000
Federal share50%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 3, 2016
2017201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Charlottetown
- Construction start
- Sep 1, 2016(actual)
- Construction end
- Feb 7, 2020(actual)
Against the original forecast
- Construction end2.5 years lateforecast Jul 30, 2017
Also in Charlottetown
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47144 in the federal list. How to read these figures.