Miltonvale Wellfield Reservoir
Charlottetown, Prince Edward Island
Federal contribution
$4.0M
$4,000,000
Federal share50%
of $8.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 3, 2016
201720182019202020212022
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Charlottetown
- Construction start
- Jun 1, 2017(actual)
- Construction end
- Dec 30, 2021(actual)