Back to projects

Miltonvale Wellfield Reservoir

Charlottetown, Prince Edward Island

completeDrinking WaterCWWF
Federal contribution
$4.0M
$4,000,000
Federal share50%

of $8.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 3, 2016
201720182019202020212022
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Charlottetown
Construction start
Jun 1, 2017(actual)
Construction end
Dec 30, 2021(actual)

Also in Charlottetown

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47160 in the federal list. How to read these figures.