Replacement of Rolling Stock and Extension to Trail Renewal
Federal contribution
$3.5M
$3,535,371
Federal share49%
of $7.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 18, 2016
201720182019
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Saint John Transit
- Construction start
- Sep 1, 2016(actual)
- Construction end
- Mar 31, 2019(actual)
Against the original forecast
- Construction start3 months earlyforecast Nov 30, 2016
- Construction end12 months lateforecast Mar 31, 2018
Also in Saint John
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47172 in the federal list. How to read these figures.