Thibodeau Road Sanitary Sewer Extension
Federal contribution
$1.4M
$1,362,858
Federal share50%
of $2.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 18, 2016
201720182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Cap-Pelé
- Construction start
- May 1, 2017(actual)
- Construction end
- Sep 30, 2019(actual)
Against the original forecast
- Construction end22 months lateforecast Nov 30, 2017
Also in Cap-Pelé
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47295 in the federal list. How to read these figures.