Extension of Sanitary Sewer System - Acadie and Saint-André Roads

Cap-Pelé, New Brunswick

completeWastewaterCWWF
Federal contribution
$1.8M
$1,803,686
Federal share48%

of $3.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
2017201820192020
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Cap-Pelé
Construction start
May 1, 2017(actual)
Construction end
Dec 31, 2019(actual)