Fairview Mall Transit Terminal
Federal contribution
$1.0M
$1,000,000
Federal share50%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 23, 2016
ApprovedMar 10, 2017
201720182019
Built
Approved 7 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Regional Municipality of Waterloo
- Construction start
- Aug 2, 2016(actual)
- Construction end
- Aug 29, 2019(actual)
Against the original forecast
- Construction end3 months lateforecast May 31, 2019
Also in Waterloo
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47416 in the federal list. How to read these figures.