Northfield Drive Transit Facility
Federal contribution
$2.1M
$2,145,742
Federal share38%
of $5.6M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 23, 2016
ApprovedMay 3, 2017
201720182019
Built
Approved 8 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Regional Municipality of Waterloo
- Construction start
- May 3, 2017(actual)
- Construction end
- Dec 31, 2018(actual)
Against the original forecast
- Construction start9 months lateforecast Aug 2, 2016
Also in Waterloo
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47418 in the federal list. How to read these figures.