Mann Avenue Transit Structure Replacement - Transit Connectivity (Rail and Bus)

Ottawa, Ontario

completePublic TransitPTIF
Federal contribution
$2.5M
$2,499,999
Federal share50%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 23, 2016
20172018201920202021
Built
Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Ottawa
Construction start
Jun 1, 2016(actual)
Construction end
Feb 9, 2021(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2016
  • Construction end23 months earlyforecast Dec 31, 2022