Carleton Siding - Spring switch replacement with new powered switches
Federal contribution
$1.3M
$1,250,000
Federal share50%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 23, 2016
2017
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Nov 10, 2016(actual)
- Construction end
- Oct 31, 2017(actual)
Against the original forecast
- Construction start7 months lateforecast Apr 1, 2016
- Construction end5 months earlyforecast Mar 31, 2018
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47432 in the federal list. How to read these figures.