Customer waiting areas at major Confederation Line stations
Federal contribution
$767,046
Federal share38%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 23, 2016
20172018
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Apr 1, 2017(actual)
- Construction end
- Mar 31, 2018(actual)
Against the original forecast
- Construction start12 months lateforecast Apr 1, 2016
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47434 in the federal list. How to read these figures.