Pave rural park and ride lot

Ottawa, Ontario

completePublic TransitPTIF
Federal contribution
$292,350
Federal share29%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 23, 2016
ApprovedMar 19, 2018
20172018
Built

Approved 19 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Ottawa
Construction start
Feb 10, 2017(actual)
Construction end
Oct 31, 2017(actual)

Against the original forecast

  • Construction start10 months lateforecast Apr 1, 2016
  • Construction end5 months earlyforecast Mar 31, 2018