Back to projects

Emergency phone upgrades at Transitway stations

Ottawa, Ontario

completePublic TransitPTIF
Federal contribution
$748,331
Federal share37%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 23, 2016
ApprovedMar 27, 2018
2017201820192020
Built

Approved 19 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Ottawa
Construction start
Apr 1, 2017(actual)
Construction end
Feb 29, 2020(actual)

Against the original forecast

  • Construction start12 months lateforecast Apr 1, 2016
  • Construction end11 months lateforecast Mar 31, 2019

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47445 in the federal list. How to read these figures.