Transitway (Busway) Pavement Resurfacing
Federal contribution
$1.6M
$1,584,891
Federal share50%
of $3.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 23, 2016
ApprovedMar 19, 2018
20172018201920202021
Built
Approved 19 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- May 1, 2017(actual)
- Construction end
- Feb 10, 2021(actual)
Against the original forecast
- Construction start13 months lateforecast Apr 1, 2016
- Construction end23 months earlyforecast Dec 31, 2022
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47450 in the federal list. How to read these figures.