Acquisition of 2 train sets
Federal contribution
$18.6M
$18,567,584
Federal share46%
of $40.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 23, 2016
20172018201920202021
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Jun 21, 2017(actual)
- Construction end
- Nov 30, 2020(actual)
Against the original forecast
- Construction start15 months lateforecast Apr 1, 2016
- Construction end8 months earlyforecast Jul 31, 2021
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47453 in the federal list. How to read these figures.