LRT Stage 2 - Bridge to grade separate VIA/O-Train Elwood diamond
Federal contribution
$646,021
Federal share26%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 23, 2016
ApprovedJul 10, 2017
201720182019202020212022
Built
Approved 11 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Apr 1, 2016(actual)
- Construction end
- Dec 31, 2021(actual)
Against the original forecast
- Construction end12 months earlyforecast Dec 31, 2022