Aboriginal consultation (including other transit and active transportation projects)
Federal contribution
$99,936
Federal share50%
of $200.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 23, 2016
ApprovedJul 10, 2017
20172018201920202021
Built
Approved 11 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Apr 1, 2016(actual)
- Construction end
- Jul 31, 2021(actual)