Back to projects

Aboriginal consultation (including other transit and active transportation projects)

Ottawa, Ontario

completePublic TransitPTIF
Federal contribution
$99,936
Federal share50%

of $200.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 23, 2016
ApprovedJul 10, 2017
20172018201920202021
Built

Approved 11 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Ottawa
Construction start
Apr 1, 2016(actual)
Construction end
Jul 31, 2021(actual)

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47457 in the federal list. How to read these figures.