Cost sharing for improvements of cycling and pedestrian links at Ministry of Transportation Ontario (MTO) overpasses

Ottawa, Ontario

completeActive TransportationPTIF
Federal contribution
$135,867
Federal share7%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 23, 2016
ApprovedMar 19, 2018
20172018
Built

Approved 19 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Ottawa
Construction start
Mar 6, 2017(actual)
Construction end
Oct 31, 2018(actual)

Against the original forecast

  • Construction start11 months lateforecast Apr 1, 2016
  • Construction end4 weeks lateforecast Sep 30, 2018

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47458 in the federal list. How to read these figures.