Chapman Mills transit corridor - Beatrice to Longfields
Federal contribution
$1.4M
$1,358,731
Federal share45%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 23, 2016
ApprovedMar 19, 2018
201720182019
Built
Approved 19 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Jun 23, 2017(actual)
- Construction end
- Nov 30, 2018(actual)
Against the original forecast
- Construction start15 months lateforecast Apr 1, 2016
- Construction end4 months earlyforecast Mar 31, 2019