Rideau River Crossing - Confederation Heights to Carleton University - pedestrian/cycling
Federal contribution
$775,000
Federal share50%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 23, 2016
ApprovedMar 30, 2017
20172018201920202021
Built
Approved 7 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Jan 1, 2017(actual)
- Construction end
- Feb 9, 2021(actual)
Against the original forecast
- Construction start9 months lateforecast Apr 1, 2016
- Construction end23 months earlyforecast Dec 31, 2022