Heron Road (Data Centre/Heron Station to Bank), Eastbound and Westbound Bike Tracks
Federal contribution
$325,000
Federal share50%
of $650.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 23, 2016
ApprovedMar 27, 2018
2017201820192020
Built
Approved 19 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- May 15, 2017(actual)
- Construction end
- Nov 30, 2019(actual)
Against the original forecast
- Construction start13 months lateforecast Apr 1, 2016
- Construction end20 months earlyforecast Jul 31, 2021