Heron Rd (Colbert Pathway to east of Jefferson) - Eastbound bike tracks only
Federal contribution
$274,999
Federal share50%
of $550.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 23, 2016
20172018201920202021
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- May 15, 2017(actual)
- Construction end
- Feb 9, 2021(actual)
Against the original forecast
- Construction start13 months lateforecast Apr 1, 2016
- Construction end23 months earlyforecast Dec 31, 2022
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47464 in the federal list. How to read these figures.