Kanata North cycle link (Carling at March Rd)

Ottawa, Ontario

completeActive TransportationPTIF
Federal contribution
$188,667
Federal share24%

of $800.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 23, 2016
ApprovedJul 10, 2017
20172018
Built

Approved 11 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Ottawa
Construction start
Feb 22, 2017(actual)
Construction end
Aug 31, 2018(actual)

Against the original forecast

  • Construction start11 months lateforecast Apr 1, 2016
  • Construction end7 months earlyforecast Mar 31, 2019

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47466 in the federal list. How to read these figures.