Kanata North cycle link (Carling at March Rd)
Federal contribution
$188,667
Federal share24%
of $800.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 23, 2016
ApprovedJul 10, 2017
20172018
Built
Approved 11 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Feb 22, 2017(actual)
- Construction end
- Aug 31, 2018(actual)
Against the original forecast
- Construction start11 months lateforecast Apr 1, 2016
- Construction end7 months earlyforecast Mar 31, 2019
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47466 in the federal list. How to read these figures.