Back to projects

Trillium Pathway extension phase 3 (Carling to Dows Lake)

Ottawa, Ontario

completeActive TransportationPTIF
Federal contribution
$222,366
Federal share40%

of $550.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 23, 2016
ApprovedMar 30, 2017
201720182019
Built

Approved 7 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Ottawa
Construction start
Sep 7, 2017(actual)
Construction end
Mar 31, 2019(actual)

Against the original forecast

  • Construction start17 months lateforecast Apr 1, 2016
  • Construction end5 months lateforecast Oct 31, 2018

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47468 in the federal list. How to read these figures.