Back to projects

Accessibility for Ontarians with Disabilities Act (AODA) Enhancements of Intersections

Ottawa, Ontario

completeActive TransportationPTIF
Federal contribution
$1.5M
$1,500,000
Federal share50%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 23, 2016
ApprovedMar 30, 2017
201720182019202020212022
Built

Approved 7 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Ottawa
Construction start
Jun 23, 2017(actual)
Construction end
Dec 15, 2021(actual)

Against the original forecast

  • Construction start15 months lateforecast Apr 1, 2016
  • Construction end13 months earlyforecast Dec 31, 2022

Also in Ottawa