Hunt Club Cycling Links (Riverside to Paul Benoit)
Federal contribution
$136,646
Federal share25%
of $550.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 23, 2016
20172018
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- May 1, 2017(actual)
- Construction end
- Mar 15, 2018(actual)
Against the original forecast
- Construction start13 months lateforecast Apr 1, 2016
- Construction end2 weeks earlyforecast Mar 31, 2018