Queen Elizabeth Drive - Crossings at Commissioner's Park and at Queen Elizabeth Place - pedestrian/cycling
Federal contribution
$374,969
Federal share50%
of $750.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 23, 2016
20172018201920202021
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Sep 1, 2016(actual)
- Construction end
- Feb 9, 2021(actual)
Against the original forecast
- Construction start5 months lateforecast Apr 1, 2016
- Construction end23 months earlyforecast Dec 31, 2022