New sidewalk links to improve connections with public transit

Ottawa, Ontario

completePublic TransitPTIF
Federal contribution
$775,000
Federal share50%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 23, 2016
2017
Built
Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Ottawa
Construction start
Dec 21, 2016(actual)
Construction end
Nov 24, 2017(actual)

Against the original forecast

  • Construction start9 months lateforecast Apr 1, 2016
  • Construction end5.1 years earlyforecast Dec 31, 2022