Cardinal Creek Park 18A multiuse pathway
Federal contribution
$540,470
Federal share42%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedAug 23, 2016
ApprovedJul 10, 2017
201720182019
Built
Approved 11 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Sep 25, 2017(actual)
- Construction end
- Nov 30, 2018(actual)
Against the original forecast
- Construction start18 months lateforecast Apr 1, 2016
- Construction end2 weeks lateforecast Nov 15, 2018
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47476 in the federal list. How to read these figures.