Cardinal Creek Park 18A multiuse pathway

Ottawa, Ontario

completeActive TransportationPTIF
Federal contribution
$540,470
Federal share42%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 23, 2016
ApprovedJul 10, 2017
201720182019
Built

Approved 11 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Ottawa
Construction start
Sep 25, 2017(actual)
Construction end
Nov 30, 2018(actual)

Against the original forecast

  • Construction start18 months lateforecast Apr 1, 2016
  • Construction end2 weeks lateforecast Nov 15, 2018