Manotick - Multil-Use Pathway (MUP) between Main St and River Rd and addition of MUP to two bridges
Federal contribution
$236,669
Federal share20%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 23, 2016
201720182019
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Mar 15, 2017(actual)
- Construction end
- Oct 31, 2019(actual)
Against the original forecast
- Construction start11 months lateforecast Apr 1, 2016
- Construction end5 months lateforecast May 31, 2019
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47477 in the federal list. How to read these figures.