Rideau Canal Crossing (Fifth to Clegg) & Ottawa River Crossing (POW Bridge) - Active Transportation (Bridges) & Transit Connectivity
Federal contribution
$10.0M
$10,045,583
Federal share48%
of $21.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 23, 2016
20172018201920202021
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Jun 1, 2017(actual)
- Construction end
- Feb 9, 2021(actual)
Against the original forecast
- Construction start14 months lateforecast Apr 1, 2016
- Construction end23 months earlyforecast Dec 31, 2022
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47489 in the federal list. How to read these figures.