Metcalfe Street Reconstruction - Phase 1

Guelph, Ontario

completeWastewaterCWWF
Federal contribution
$1.6M
$1,583,804
Federal share44%

of $3.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 14, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Construction start
May 15, 2017(actual)
Construction end
Dec 31, 2018(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Jun 1, 2017
  • Construction end6 months lateforecast Jun 29, 2018

Also in Guelph

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47530 in the federal list. How to read these figures.