Metcalfe Street Reconstruction - Phase 1
Federal contribution
$1.6M
$1,583,804
Federal share44%
of $3.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 14, 2016
201720182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- The Corporation of The City of Guelph
- Construction start
- May 15, 2017(actual)
- Construction end
- Dec 31, 2018(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Jun 1, 2017
- Construction end6 months lateforecast Jun 29, 2018