Schedule

Announced and approvedSep 14, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Construction start
Oct 3, 2016(actual)
Construction end
Jun 30, 2020(actual)

Against the original forecast

  • Construction start19 months earlyforecast May 1, 2018
  • Construction end15 months earlyforecast Sep 30, 2021