Etobicoke Creek Valley Landfill Study for two landfills (technical data) to analyze and document the condition of the landfill to support the City's Downtown Revitalization

Brampton, Ontario

completeWastewaterCWWF
Federal contribution
$46,158
Federal share46%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 14, 2016
ApprovedJul 10, 2017
201720182019
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Sep 1, 2017(actual)
Construction end
Jan 31, 2019(actual)

Against the original forecast

  • Construction start2 months lateforecast Jul 2, 2017
  • Construction end8 weeks earlyforecast Mar 31, 2019

Also in Brampton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47543 in the federal list. How to read these figures.