Back to projects

Pond Rehabilitation at the Upper 9 stormwater management facility

Brampton, Ontario

completeWastewaterCWWF
Federal contribution
$449,807
Federal share50%

of $900.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 14, 2016
ApprovedJul 10, 2017
2017201820192020
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jul 2, 2017(actual)
Construction end
Jan 28, 2020(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Dec 31, 2019

Also in Brampton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47548 in the federal list. How to read these figures.