Rehabilitation of streambanks within the Etibicoke Creek Watershed

Brampton, Ontario

completeWastewaterCWWF
Federal contribution
$949,211
Federal share47%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 14, 2016
ApprovedJul 10, 2017
2017201820192020
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jul 2, 2017(actual)
Construction end
Jan 28, 2020(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Dec 31, 2019