Back to projects

Hotchkiss Creek Expansion- Essa, Anne to Gowan

Barrie, Ontario

completeWastewaterCWWF
Federal contribution
$2.7M
$2,713,614
Federal share33%

of $8.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 14, 2016
ApprovedFeb 26, 2018
20172018
Built

Approved 17 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Barrie
Construction start
Apr 1, 2016(actual)
Construction end
Jul 13, 2018(actual)

Against the original forecast

  • Construction start9 months earlyforecast Jan 1, 2017
  • Construction end3 months lateforecast Mar 31, 2018

Also in Barrie

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47567 in the federal list. How to read these figures.