1st Avenue - upgrade to main water line in Coniston
Federal contribution
$1.9M
$1,935,000
Federal share50%
of $3.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 14, 2016
201720182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Greater Sudbury
- Construction start
- Nov 14, 2016(actual)
- Construction end
- Mar 31, 2019(actual)
Also in Greater Sudbury