York Street - Regent Street to Paris Street - Water Main Lining

Greater Sudbury, Ontario

completeDrinking WaterCWWF
Federal contribution
$249,925
Federal share50%

of $499.8K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 14, 2016
ApprovedMar 27, 2018
20172018
Built

Approved 18 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Greater Sudbury
Construction start
Oct 10, 2017(actual)
Construction end
Sep 30, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast May 1, 2017
  • Construction end3 months lateforecast Jun 30, 2018