Strathmere Court - Robinson Drive East to Robinson Drive West - Water Main Lining

Greater Sudbury, Ontario

completeDrinking WaterCWWF
Federal contribution
$125,000
Federal share50%

of $250.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 14, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Greater Sudbury
Construction start
Oct 10, 2016(actual)
Construction end
Sep 30, 2018(actual)

Against the original forecast

  • Construction start7 months earlyforecast May 1, 2017
  • Construction end11 months lateforecast Oct 15, 2017