Manninen Road - Culvert Replacement
Federal contribution
$49,206
Federal share49%
of $100.3K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 14, 2016
ApprovedMar 27, 2018
20172018
Built
Approved 18 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Greater Sudbury
- Construction start
- Sep 18, 2017(actual)
- Construction end
- Nov 19, 2018(actual)
Against the original forecast
- Construction start5 months lateforecast May 1, 2017
- Construction end13 months lateforecast Oct 15, 2017
Also in Greater Sudbury
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47579 in the federal list. How to read these figures.