Schedule

AnnouncedSep 14, 2016
ApprovedMar 27, 2018
20172018
Built

Approved 18 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Greater Sudbury
Construction start
Oct 15, 2017(actual)
Construction end
Nov 19, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast May 1, 2017
  • Construction end11 months lateforecast Dec 15, 2017

Also in Greater Sudbury