MR55 - Culvert Replacement #1553
Federal contribution
$550,101
Federal share49%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 14, 2016
ApprovedMar 27, 2018
20172018
Built
Approved 18 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Greater Sudbury
- Construction start
- Jun 29, 2017(actual)
- Construction end
- Sep 30, 2018(actual)
Against the original forecast
- Construction start8 weeks lateforecast May 1, 2017
- Construction end11 months lateforecast Oct 15, 2017