York Street - Regent Street to Paris Street - Sewer Main Lining
Federal contribution
$50,434
Federal share47%
of $106.3K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 14, 2016
ApprovedMar 27, 2018
20172018
Built
Approved 18 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Greater Sudbury
- Construction start
- Oct 10, 2017(actual)
- Construction end
- Sep 30, 2018(actual)
Against the original forecast
- Construction start5 months lateforecast May 1, 2017
- Construction end3 months lateforecast Jun 30, 2018