David Street - Storm Water Outlet Treatment Station - Design & Construction
Federal contribution
$465,929
Federal share29%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 14, 2016
ApprovedMar 27, 2018
2017201820192020
Built
Approved 18 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Greater Sudbury
- Construction start
- Oct 3, 2017(actual)
- Construction end
- Dec 31, 2019(actual)
Against the original forecast
- Construction start12 months lateforecast Oct 15, 2016
- Construction end9 months earlyforecast Sep 30, 2020
Also in Greater Sudbury