Pincher Creek - Beaver Mines Regional Water Supply
Federal contribution
$2.3M
$2,288,403
Federal share50%
of $4.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 1, 2016
201720182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipal District of Pincher Creek
- Construction start
- Jul 31, 2016(actual)
- Construction end
- Jun 7, 2019(actual)
Against the original forecast
- Construction start7 months earlyforecast Mar 1, 2017
Also in Beaver Mines
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47594 in the federal list. How to read these figures.