Hamlet of Beaver Mines Treated Water Storage
Federal contribution
$180,330
Federal share50%
of $360.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 15, 2018
201820192020
Built
Approved 7 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipal District of Pincher Creek
- Construction start
- Jan 2, 2018(actual)
- Construction end
- May 22, 2020(actual)
Against the original forecast
- Construction end7 months lateforecast Oct 31, 2019
Also in Beaver Mines
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51717 in the federal list. How to read these figures.