Water and Waste Water Infrastructure assessment
Norman Wells, Northwest Territories
Federal contribution
$75,044
Federal share38%
of $200.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 6, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Norman Wells
- Construction start
- Jun 1, 2017(actual)
- Construction end
- Aug 9, 2018(actual)
Against the original forecast
- Construction start8 months lateforecast Oct 1, 2016
- Construction end5 months lateforecast Feb 28, 2018
Also in Norman Wells
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47613 in the federal list. How to read these figures.